Skip to content

Government Notices and Plans Issued by Lands Department for Land Acquisition and Foreshore and Seabed Reclamation (Since 2 January 2009)

Publication DateProject TitleType of Government NoticeGovernment NoticeRelated Gazette Plan
(Note)
28 December 2012PWP Item No. 339DS −
North District Sewerage Stage 1 Phase 2C and Stage 2 Phase 1 (Part) − Village Sewerage Works in Ping Kong, Sheung Shui, New Territories
Creation of Rights of Temporary Occupation of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 8296DNM2212c
28 December 2012PWP Item No. 339DS −
North District Sewerage Stage 1 Phase 2C and Stage 2 Phase 1 (Part) − Village Sewerage Works in Ping Kong, Sheung Shui, New Territories
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Chapter 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 8295DNM2211d
23 November 2012Public Works Programme Item No. 469CL Kai Tak Development - Infrastructure at North Apron Area of Kai Tak Airport - Stage 4 Infrastructure Works Reconstruction of Existing Seawall near To Kwa Wan Typhoon ShelterAuthorization under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 7561KM8773
16 November 2012PWP Item No. 4353DS Outlying Islands Sewerage Stage 2 –
Stage 2 – Upgrading of Mui Wo Village Sewerage Phase 2 and Mui Wo Sewage Treatment Works (Wang Tong and Mui Wo Centre) Corrigendum
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Chapter 370) as Applied by Section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 7481ISM1659h_1
(Sheet 1 of 2) &
ISM1659h_2
(Sheet 2 of 2)
9 November 2012Proposed Construction Works of a Platform for The Hong Kong Federation of Youth Groups Jockey Club Sai Kung Outdoor Training Camp at Tai Mong Tsai, Sai Kung, New TerritoriesAuthorization under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 7284SKM7947b
9 November 2012Providing Sufficient Water Depth for Kwai Tsing Container Basin and its Approach ChannelAuthorization under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 7283KTM1492a
2 November 2012PWP Item No. 4125DS -
Tolo Harbour Sewerage of Unsewered Areas Stage I Phase IIC - Village Sewerage at San Tau Kok, Po Sam Pai and Lai Pek Shan San Tsuen, Tai Po
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 7126TPM4819b_1
(Sheet 1 of 2) &
TPM4819b_2
(Sheet 2 of 2)
5 October 2012Development of a Bathing Beach at Lung Mei, Tai PoAuthorization under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 6605TPM4654
21 September 2012Proposed External Lift at Shek Kip –Mass Transit Railway ('MTR') Station Improvement WorksRoad Closure and Alteration under Mass Transit Railway (Land Resumption And Related Provisions) Ordinance (Chapter 276)G.N. 6328KM8192a
21 September 2012 and 28 September 2012Mass Transit Railway (‘MTR’) South Island Line (East)Resumption of Land under Railways Ordinance (Chapter 519)G.N. 6265RDM1472
14 September 2012Liantang / Heung Yuen Wai Boundary Control Point and Associated WorksAcquisition of Land under the Land Acquisition (Possessory title) Ordinance (Chapter 130)G.N. 6108DNM2595a_1
(Sheet 1 of 9) &
DNM2595a_2
(Sheet 2 of 9) &
DNM2595a_3
(Sheet 3 of 9) &
DNM2595a_4
(Sheet 4 of 9) &
DNM2595a_5
(Sheet 5 of 9) &
DNM2595a_6
(Sheet 6 of 9) &
DNM2595a_7
(Sheet 7 of 9) &
DNM2595a_8
(Sheet 8 of 9)
DNM2595a_9
(Sheet 9 of 9
14 September 2012Liantang / Heung Yuen Wai Boundary Control Point and Associated WorksNotice of Intention to make an order under the Public Health and Municipal Services Ordinance (Chapter 132) directing the removal and disposal of human remains from graves/ urnsG.N. 6059DNM2596b_1
(Sheet 1 of 11) &
DNM2596b_2
(Sheet 2 of 11) &
DNM2596b_3
(Sheet 3 of 11) &
DNM2596b_4
(Sheet 4 of 11) &
DNM2596b_5
(Sheet 5 of 11) &
DNM2596b_6
(Sheet 6 of 11) &
DNM2596b_7
(Sheet 7 of 11) &
DNM2596b_8
(Sheet 8 of 11)
DNM2596b_9
(Sheet 9 of 11)
DNM2596b_10
(Sheet 10 of 11)
DNM2596b_11
(Sheet 11 of 11)
24 August 2012PWP Item No. 4339DS(Part) -
North District Sewerage, Stage 2 Phase 1
Village Sewerage at Tai Wo and Kau Lung Hang Lo Wai, Tai Po
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 5636TPM5127b
17 August 2012 and 24 August 2012Proposed Construction Works of a platform for the Hong Kong Federation of Youth Groups Jockey Club Sai Kung Outdoor Training Camp at Tai Mong Tsai, Sai Kung, New TerritoriesNotification under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 5544SKM7947b
17 August 2012PWP Item No. 4353DS Outlying Islands Sewerage Stage 2 -
Upgrading of Mui Wo Village Sewerage Phase 2 and Mui Wo Sewage Treatment Works (Wang Tong and Mui Wo Centre)
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Chapter 370) as Applied by Section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 5477ISM1659g_1
(Sheet 1 of 2) &
ISM1659g_2
(Sheet 2 of 2)
10 August 2012 and 17 August 2012PWP Item No. 469CL -
Kai Tak Development Infrastructure at North Apron Area of Kai Tak Airport - Stage 4 Infrastructure Works Reconstruction of Existing Seawall near To Kwa Wan Typhoon Shelter
Notification under Foreshore and Sea-bed (Reclamations) Ordinance (Cap. 127)G.N. 5388KM8773
3 August 2012Resumption of Land for Implementation of Development Scheme MK/01 by the Urban Renewal Authority at Shanghai Road / Argyle Street, Mong kok, KowloonResumption of Land under Lands Resumption Ordinance (Cap. 124)G.N. 5234
&
G.N. 5235
KM8762
&
KM8763
3 August 2012Shatin to Central LinkCreation of Rights of Temporary Occupation of Land under Railways Ordinance (Chapter 519)G.N. 5182RDM1423
27 July 2012 and 3 August 2012Providing Sufficient Water Depth For Kwai Tsing Container Basin and Its Approach ChannelNotification under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 5059KTM1492a
20 July 2012PWP Item No. 4332DS -
Lam Tsuen Valley Sewerage - Village Sewerage at Fong Ma Po, Chung Uk Tsuen, San Uk Tsai, Tong Sheung Tsuen and She Shan, Tai Po
Creation of Rights of Temporary Occupation of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Cap. 358 Subsidiary Legislation)G.N. 4851TPM5061b
20 July 2012PWP Item No. 4332DS -
Lam Tsuen Valley Sewerage - Village Sewerage at Fong Ma Po, Chung Uk Tsuen, San Uk Tsai, Tong Sheung Tsuen and She Shan, Tai Po
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Cap. 358 Subsidiary Legislation)G.N. 4850TPM5060d
29 June 2012Development of a Bathing Beach at Lung Mei, Tai PoResumption of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370)G.N. 4421TPM4661b
29 June 2012PWP Item No. 4272DS -
Port Shelter Sewerage, Stage 2, Package B, Sewerage at Wo Tong Kong, San Uk, Nam Shan, Sha Kok Mei and Kap Pin Long
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Chapter 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 4420SKM7144c
22 June 2012Development of a Bathing Beach at Lung Mei, Tai PoResumption of Land under Lands Resumption Ordinance (Chapter 124)G.N. 4321TPM4553b
22 June 2012Proposed Asia Submarine-Cable Express from Tseung Kwan O to the Eastern Boundary of the Hong Kong Special Administrative Region WatersAuthorization under Foreshore and Sea-bed (Reclamations) Ordinance (Cap. 127)G.N. 4315SKM8022a
22 June 2012Liantang / Heung Yuen Wai Boundary Control Point and Associated WorksCreation of Easements and Other Permanent Rights under Roads (Works, Use and Compensation) Ordinance (Cap. 370)G.N. 4235DNM2357b_1
(Sheet 1 of 3) &
DNM2357b_2
(Sheet 2 of 3) &
DNM2357b_3
(Sheet 3 of 3)
22 June 2012Liantang / Heung Yuen Wai Boundary Control Point and Associated WorksResumption of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370)G.N. 4234DNM2356c_1
(Sheet 1 of 16) &
DNM2356c_2
(Sheet 2 of 16) &
DNM2356c_3
(Sheet 3 of 16) &
DNM2356c_4
(Sheet 4 of 16) &
DNM2356c_5
(Sheet 5 of 16) &
DNM2356c_6
(Sheet 6 of 16) &
DNM2356c_7
(Sheet 7 of 16) &
DNM2356c_8
(Sheet 8 of 16)
&
DNM2356c_9
(Sheet 9 of 16)
&
DNM2356c_10
(Sheet 10 of 16)
&
DNM2356c_11
(Sheet 11 of 16)
&
DNM2356c_12
(Sheet 12 of 16)
&
DNM2356c_13
(Sheet 13 of 16)
&
DNM2356c_14
(Sheet 14 of 16)
&
DNM2356c_15
(Sheet 15 of 16)
&
DNM2356c_16
(Sheet 16 of 16)
15 June 2012Resumption of Land for Implementation of Development Project MTK/1/002 by the Urban Renewal Authority at San Shan Road / Pau Chung Street, Ma Tau Kok, KowloonResumption of Land under Lands Resumption Ordinance (Cap. 124)G.N. 4130KM8729
8 June 2012Proposed External Lift at Sai Wan Ho Station –Mass Transit Railway ('MTR') Station Improvement WorksRoad Closure and Alteration under Mass Transit Railway (Land Resumption And Related Provisions) Ordinance (Chapter 276)G.N. 3930
&
G.N. 3931
HKM9265
1 June 2012Construction of a Landing and Access Facility at Che Lei Pai Beacon, Tolo Channel, Tai PoAuthorization under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 3746TPM5441b
4 May 2012PWP Item No. 7710CL Hung Shui Kiu Development, Stage 2 –
Widening of Tin Ha Road and Tan Kwai Tsuen Road (Portion for Tan Kwai Tsuen Road)
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370)G.N. 2976YLM7677a
4 May 2012Improvement of Kam Pok Road – Man Yuen Chuen SectionResumption of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370)G.N. 2975YLM7579b
27 April 2012PWP Item No. 834TH Hong Kong -
Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities
Creation of Easements and Other Permanent Rights and Rights of Temporary Occupation of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370)G.N. 2764ISM1734b-I
&
ISM1732b-I
(Sheet 1 of 3) &
ISM1732b-I
(Sheet 2 of 3) &
ISM1732b-I
(Sheet 3 of 3)
27 April 2012PWP Item No. 844TH Hong Kong -
Zhuhai - Macao Bridge Hong Kong Link Road
Creation of Easements and Other Permanent Rights and Rights of Temporary Occupation of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370)G.N. 2763ISM1742a
(Sheet 1 of 3) &
ISM1742a
(Sheet 2 of 3) &
ISM1742a
(Sheet 3 of 3) &
ISM1757a
(Sheet 1 of 5) &
ISM1757a
(Sheet 2 of 5) &
ISM1757a
(Sheet 3 of 5) &
ISM1757a
(Sheet 4 of 5) &
ISM1757a
(Sheet 5 of 5)
27 April 2012PWP Item No. 834TH Hong Kong -
Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370)G.N. 2762ISM1731a-I
(Sheet 1 of 2) &
ISM1731a-I
(Sheet 2 of 2)
27 April 2012PWP Item No. 844TH Hong Kong -
Zhuhai - Macao Bridge Hong Kong Link Road
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Cap. 370)G.N. 2761ISM1741a
(Sheet 1 of 3) &
ISM1741a
(Sheet 2 of 3) &
ISM1741a
(Sheet 3 of 3)
27 April 2012PWP Item No. 4345DS –
North District Sewerage Stage 2 Part 2A (PART) – Village Sewerage In Sheung Tam Shui Hang and Ha Tam Shui Hang, Sha Tau Kok, New Territories
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Chapter 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 2760DNM2273a
20 April 2012PWP Item No. 4272DS Port Shelter Sewerage, Stage 2, Package C, Sewerage at Tai Ping Tsuen and Tai Shui TsengResumption of Land under Roads (Works, Use and Compensation) Ordinance (Chapter 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 2547SKM7138b
20 April 2012Proposed South-East Asia Japan Cable System From Sha Shek Tan at Chung Hom Kok to Eastern Boundary of the Hong Kong Special Administrative RegionAuthorization under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 2639HKM9274
13 April 2012PWP Item no.4274DS
Yuen Long and Kam Tin Sewerage Stage 3-Village Sewerage at Tai Tong Tsuen, Yuen Long
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Chapter 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 2370YLM7710a
23 March 2012PWP Item No. 5177DR -
Dredging and Reclamation to the South-western Coast of Shek Kwu Chau for the Integrated Waste Management Facilities Phase 1 (IWMF – PHASE 1)
Authorization under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 1901ISM2069b
16 March 2012 and 23 March 2012Proposed Asia Submarine - Cable Express from Tseung Kwan O to The Eastern Boundary of The Hong Kong Special Administrative Region WatersNotification under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 1679SKM8022a
2 March 2012 and 9 March 2012Mass Transit Railway (‘MTR’) Kwun Tong Line ExtensionResumption of Underground Strata of Land under Railways Ordinance (Chapter 519)G.N. 1298RDM1344
&
RDM1345
2 March 2012Resumption of Land for Implementation of the First Phase of the Kwun Tong Town Centre – Main Site Development Scheme by the Urban Renewal Authority at Kwun Tong, KowloonResumption of Land under Lands Resumption Ordinance (Chapter 124)G.N. 1296
&
G.N. 1297
KM8645
(Sheet 1 of 2) &
KM8645
(Sheet 2 of 2) &
KM8646
2 March 2012Shoreline Stabilisation Works at Butterfly Beach, Tuen MunAuthorization under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 1295TMM3354
2 March 2012PWP Item no.4274DS -
Yuen Long and Kam Tin Sewerage Stage 3-Village Sewerage at Nam Pin Wai, Sai Pin Wai and Ying Lung Wai, Yuen Long
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Chapter 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 1152YLM7402b
(Sheet 1 of 2) &
YLM7402b
(Sheet 2 of 2)
24 February 2012Proposed External Lift at Prince Edward Station –Mass Transit Railway ('MTR') Station Improvement WorksRoad Closure and Alteration under Mass Transit Railway (Land Resumption And Related Provisions) Ordinance (Chapter 276)G.N. 1058
&
G.N. 1059
KM8606
24 February 2012Proposed External Lift at Lai Chi Kok Station –Mass Transit Railway ('MTR') Station Improvement WorksRoad Closure and Alteration under Mass Transit Railway (Land Resumption And Related Provisions) Ordinance (Chapter 276)G.N. 1056
&
G.N. 1057
KM8320
17 February 2012 and 24 February 2012Construction of a Landing and Access Facility at To Tau Tsui Beacon, TOLO Channel, Tai Po Notification under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 878TPM5446b
17 February 2012 and 24 February 2012Construction of a Landing and Access Facility at Fung Wong Wat Beacon, TOLO Channel, Tai Po Notification under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 877TPM5450b
17 February 2012PWP Item no. 5013GB - Regulation of Shenzhen River Stage 4 – Ancillary Road WorksResumption of Land under Roads (Works, Use and Compensation) Ordinance (Chapter 370)G.N. 790DNM2375a
(Sheet 1 of 6) &
DNM2375a
(Sheet 2 of 6) &
DNM2375a
(Sheet 3 of 6) &
DNM2375a
(Sheet 4 of 6) &
DNM2375a
(Sheet 5 of 6) &
DNM2375a
(Sheet 6 of 6)
17 February 2012Mass Transit Railway (‘MTR’) South Island Line (East)Resumption of Underground Strata of Land under Railways Ordinance (Chapter 519)G.N. 788RDM1351
(Sheet 1 of 3) &
RDM1351
(Sheet 2 of 3)
&
RDM1351
(Sheet 3 of 3)
10 February 2012Regulation of Shenzhen River Stage 4 – River Channel Works
Resumption of Land under Lands Resumption Ordinance (Chapter 124)
G.N. 703DNM2374
(Sheet 1 of 6) &
DNM2374
(Sheet 2 of 6) &
DNM2374
(Sheet 3 of 6) &
DNM2374
(Sheet 4 of 6) &
DNM2374
(Sheet 5 of 6) &
DNM2374
(Sheet 6 of 6)
27 January 2012Improvement Works to the Public Landing Facility at Trio Beach, Sai KungAuthorization under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 454SKM7637
20 January 2012 and 27 January 2012Proposed South-East Asia Japan Cable System from Sha Shek Tan at Chung Hom Kok to Eastern Boundary of the Hong Kong Special Administrative RegionNotification under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 341HKM9274
20 January 2012 and 27 January 2012Construction of a Landing and Access Facility at Che Lei Pai Beacon, TOLO Channel, Tai PoNotification under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127)G.N. 340TPM5441b
20 January 2012PWP Item no. 4345DS –
North District Sewerage Stage 2 Part 2A (PART) – Village Sewerage in Shan Tsui, Sha Tau Kok, New Territories
Resumption of Land under Roads (Works, Use and Compensation) Ordinance (Chapter 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358 Subsidiary Legislation)G.N. 280DNM2266a

Note :

The Gazette Plans can also be inspected by public free of charge at the offices as specified under the respective Government Notices or be purchased at the Lands Department Map Sales Outlets.

Get Adobe Acrobat Reader software
To view or print the above download document (PDF file), you need to use Adobe Acrobat Reader software. Please update your version of Adobe Acrobat Reader software if you have problem in viewing the downloaded PDF file.